NTPC MOUDA SITE PROGRESS
  CIVIL COMPLETION STR. COMPLETION EQUIPMENT COMPLETION
WAGON TIPPLER AREA: 80% --------- JUST STARTED
CRUSHER HOUSE RCC FLOOR 60% 90% COMPL 4NOS. CRUSHERS ERECTED
STACKER RECLAIMER STACKER 1 60% COMPL. --------- 20% COMPL
CONVEYOR'S      
1AB COML. ---------  
2AB COML. 95% COMPL. 50% COMPL.
3AB COML. 95% COMPL. 80% COMPL.
4AB COML. JUST STARTED ---------
5AB COML. 85% COMPL. 50% COMPL.
6AB COML. 90% COMPL. 40% COMPL.
8AB COML. 50% COMPL. 50% COMPL.
13AB COML. 90% COMPL 30% COMPL
TRANSFER TOWER      
TP-1 COML. ---------  
TP-2 COML. 50% COMPL.  
TP-3 COML. 90% COMPL. 85% COMPL.
TP-4 COML. 85% COMPL. 40% COMPL.
TP-5 COML. 95% COMPL. 95% COMPL.
TP-6 COML. 80% COMPL. 30% COMPL.
TP-7 COML. 40% COMPL. ---------
TP-13 COML. 95% COMPL 90% COMPL