NTPC, BARH


Progress at TRF’ NTPC BARH Site TRF has made continuous progress to fulfill its commitment to set up the coal handling plant at Barh – NTPC’s site for its 2X660 MW thermal power plant. The order is for design, engineering, manufacturing, supplying, erecting, testing and commissioning of a coal handling plant on a turn-key basis. The plant is designed to run at coal handling capacity of 2200 tonnes per hour. We bring to you a brief report of ‘on-ground’ activities at the site till October 2011... Read More
 

Contact Us      Site Map        Links      Search
Copyright ©2005 TRF Ltd, A Tata Enterprise. || Webmaster: Head, Corporate Communications (rajen.sahay@trf.co.in) || Hosted & Powered by: SparX Technologies Pvt. Ltd.