NTPC Vindhyachal Site Progress Report
Click here for Photo Gallery | Back
NTPC-VINDHYACHAL SITE PROGRESS
TRACK HOPPER AREA 3 segments of 700 cum each casted,Walls of first lift of 2.4m height of 1st segment completed .
WAGON TIPPLER AREA First raft of 500 cum casted,3.715m wall constructed,
CRUSHER HOUSE AREA All pilling completed,foundations ready for annexure part & balance foundation work in progress for main crusher house.
STACKER RECLAIMER AREA Piling & Excavation in progress,
TP-34 Fabrication completed 100 %& erection under progress
TP-35 Fabrication 90 % completed and erection under progress.